sections in the article
When working with Tasks, it is a common requirement to simply work through all of the linked Entities one by one until the activity is completed. A simple way to do this is as follows:
1. Click on the Task you want to work with | |
2. In the Includes tab of the Task, Click menu icon of the Entity Section, and select Open in work area. |
|
3. The list of Entities will now remain available in the left-hand panel as your to-do list as you work. | |
4. As you complete each activity, you can remove the Entity from the Work Area. It will remain linked to the Task as a record of what you have completed. |
Further reading
Glossary article on Task